Mandatory Occurrence Reporting is one of the most misunderstood obligations under the Building Safety Act 2022 regime. Construction teams that have operated successfully under CDM and conventional building control for years often approach MOR as though it were similar to accident reporting or non-conformance records. It is not. MOR is a statutory notification obligation to the Building Safety Regulator, with specific triggers, specific timeframes and specific consequences for non-compliance.

This guide sets out what MOR is, what triggers a report, who must report, how to report, and how to build MOR into your site management processes from the outset.

What Is MOR and What Is Its Legal Basis?

Mandatory Occurrence Reporting is the obligation, under Regulation 38A of the Building Regulations 2010 (as inserted by the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023), to notify the BSR when a "reportable occurrence" takes place on or in relation to a higher-risk building during the construction phase.

The obligation flows from the Building Safety Act 2022 and sits alongside the change control plan as a mechanism for ensuring that the BSR maintains oversight of what is happening on site after Gateway 2 approval has been granted. It is not a voluntary safety management tool — it is a compulsory statutory notification regime.

The MOR obligation applies from the point at which Gateway 2 approval is granted until a Completion Certificate is issued at Gateway 3. Any work on the building that falls within the scope of the Building Regulations — which, for an HRB, means essentially all construction activities — is within the scope of MOR.

Who Is Required to Report?

The reporting obligation falls on the Principal Contractor as the primary duty holder during the construction phase. However, the obligation extends to all duty holders who become aware of a reportable occurrence. In practice, this means:

What Constitutes a Reportable Occurrence?

This is where most confusion arises. A reportable occurrence is defined under the HRB Procedures Regulations as an occurrence in relation to a higher-risk building during its construction that:

The obligation is deliberately broad. The BSR's guidance makes clear that, in cases of doubt, the duty holder should report. The regulator has stated that it will not penalise over-reporting — but will take action against duty holders who fail to report occurrences that objectively should have been notified.

Examples of events that should trigger a MOR assessment include: discovery of a structural defect in a load-bearing element; installation of a fire door that does not match the approved specification; a cavity barrier found to be incorrectly installed over a significant area; a drainage or waterproofing failure that affects a fire-rated floor; or a cladding specification change during procurement that departs from the approved fire strategy.

Reporting Timeframes and Format

Once a reportable occurrence has been identified, the Principal Contractor must notify the BSR within 10 working days. The notification must include:

  1. A description of the occurrence and how it was identified
  2. The location and extent of the occurrence within the building
  3. An assessment of whether and how the occurrence affects compliance with the Building Regulations or the approved Gateway 2 design
  4. The proposed remedial action and timescale
  5. Confirmation of whether any work has been paused pending the BSR's response

The report is submitted through the BSR's online portal. It should be clear, factual and contain sufficient information for the BSR's case officers to assess the significance of the occurrence without needing to request further information.

Site MOR Decision Process

  1. Non-conformance or potential deviation identified on site
  2. Site manager/quality manager logs the event and notifies the project's compliance lead
  3. Compliance lead assesses against the MOR trigger criteria in the MOR plan
  4. If reportable: report prepared and submitted to BSR within 10 working days
  5. If not reportable: reasoning documented in the non-conformance register; reviewed at next Gateway 3 audit
  6. If change is also required: change control plan process triggered in parallel

Relationship with the Change Control Plan

MOR and the change control plan (CCP) are related but distinct obligations. A change to the approved design that is managed through the CCP process may or may not also be a reportable occurrence. The test for MOR is whether there is a safety-critical concern. The test for change control is whether the change departs from the approved design in a way that requires BSR consent before the change is implemented.

Where an occurrence involves both a reportable event and a notifiable change, both obligations must be discharged in parallel. The MOR report and the change control submission should cross-reference each other. Submitting one without the other where both are triggered is a compliance failure.

Consequences of Non-Reporting

Failure to report a reportable occurrence is a criminal offence under the Building Safety Act 2022. The Principal Contractor and individual directors responsible for the construction phase can be prosecuted. The BSR has stated publicly that enforcement action for MOR failures is a priority area. In addition to criminal exposure, non-reporting can constitute grounds for the BSR to withdraw Gateway 2 approval and require the construction phase to stop.

Building MOR into Your Site Management Processes

The most effective MOR regimes are those that are embedded into existing quality management and non-conformance reporting processes — not operated as a separate system. Effective practice includes:

Applicable Legislation and Guidance

Primary legislation: Building Safety Act 2022
Secondary legislation: Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (SI 2023/909), Regulation 38A and Schedule 3
BSR guidance: HSE Mandatory Occurrence Reporting Guidance (current edition); BSR Construction Phase Compliance Guide
Related obligations: Change Control Plan (Regulation 17 of SI 2023/909)

MOR is not optional and it is not administrative. It is a fundamental component of the building safety regime — the mechanism by which the BSR maintains real-time oversight of construction on higher-risk buildings. Getting MOR right from day one of construction is not only a legal obligation; it is the foundation of a credible Gateway 3 application.